On November 4, 2008 and November 4, 2014, Prop V and Measure L (respectively) were authorized by LUSD District voters to issue General Obligation Bonds pursuant to a 55% vote in a bond election. These bonds were approved by voters for facility and infrastructure improvements to our schools.
Citizens Bond Oversight Committee (CBOC)
As a requirement of the bond, the district has established a Bond Oversight Committee to oversee bond expenditures and scope. If you have questions regarding the CBOC, please call (619) 390-2640.
CBOC 2024 – 2025 Meeting Dates
October 23rd, 2024– District Board Room- March 26th, 2025 – Review Audit Report, District Board Room
- May 28th, 2025 – Review CBOC Annual Report, District Board Room
*Meetings are held the last Wednesday of the month at 4:30 pm unless otherwise noted.
CBOC Meeting Agendas & Minutes
2024 – 2025
May 28th, 2025 | ||
March 26th, 2025 | ||
Meeting Cancelled | Meeting Cancelled |
2020 – 2021
2019 – 2012
September 25, 2019 | Agenda | Minutes |
May 29, 2019 | Agenda | Minutes |
May 8, 2019 | Agenda | Minutes |
May 30, 2018 | Agenda | Minutes |
April 25, 2018 | Agenda | Minutes |
May 31, 2017 | Agenda | |
April 26, 2017 | Agenda | Minutes |
June 8, 2016 | Minutes | |
May 4, 2016 | Minutes | |
June 2, 2015 | Agenda | Minutes |
May 27, 2014 | Agenda | Minutes |
April 9, 2014 | Agenda | Minutes |
June 3, 2013 | Agenda | |
April 29, 2013 | Agenda | Minutes |
December 3, 2012 | Agenda | Minutes |
September 17, 2012 | Agenda | Minutes |
July 25, 2012 | Agenda | Minutes |
April 30, 2012 | Agenda | Minutes |
February 6, 2012 | Agenda | Minutes |
Reports & Audits
Annual Reports
Current Projects
2023 – 2024 Bond Projects
Project | Location | Start Date | Completion Date | Project Description | Project Progress |
---|---|---|---|---|---|
Infrastructure Modernization and Utility Savings Program | District Wide | 3/2022 | 6/30/2024 | Project will consist of District-wide solar structures, lighting modernization, roof replacements, high efficiency HVAC units, and building automation systems implemented as utility savings measures and renewable energy generation throughout the district facilities. | 100% complete |
Recently Completed
Photo Gallery
Past Projects
2021 – 2022
Ribbon cuttings
- Lakeside Farms Elementary Modernization-Office Building, Kitchen
- Lindo Park Modernization-Multi Purpose Room, Kitchen
- Tierra Del Sol Middle School-New Gymnasium, Multi-Purpose Room
2020 – 2021
- Central Kitchen – Phase I – New Freezer, New Refrigerator, (2) Single Use Restrooms Added
- Parking Lot Upgrade (4) Sites: Eucalyptus Hills, Lakeview, Lemon Crest, Riverview
2019 – 2020
- All sites – Replacement of SmartBoards with flat-panel monitors and Apple TV’s in all classrooms.
- Shade Structures – Eucalyptus Hills & Winter Gardens received playground shade shelters.
- Flooring Replacement – Lakeside Farms received new flooring in all classrooms. Lakeside Middle School, Old Hall Building, had original wood floors resurfaced, and new carpet was installed in the hallway.
- Lakeside Middle School – New roof was installed on the Old Hall Building.
- Fire Alarm Upgrades – Eucalyptus Hills and Winter Gardens upgraded code-compliant fire alarm systems.
- HVAC – Lindo Park installed 13 new air conditioning units on portable buildings.
- Vacant Lot Clean-Up – Vacant lot adjacent to Lakeside Farms was cleaned up and graded (to prepare for future asphalt parking lot).
- Video Surveillance System Upgrade – District-Wide surveillance system was upgraded and new cameras were installed.
2018 – 2019
The 2018-2019 year included planning activities and quick start construction projects that began but were not completed until the 2019-2020 school year.
2017 – 2018
The 2017-2018 fiscal year was primarily a planning year for future bond projects pending the sale of Measure L, Series B bonds in the fall of the 2017-2018 fiscal year. The District formed a Facilities Advisory Committee and paid for Consultants to develop a Long-Range Facilities Master Plan.